Hello Marcos,
Offshore construction work for Coastal Virginia Offshore
Wind (CVOW) commenced in late February 2024 with the first seabed
disturbing activity — the relocation of the first
Munition of Explosive Concern.
The goal of our monthly email updates is to give a
high-level overview of ongoing and planned near-term construction
activities and the vessels involved. Questions regarding construction
operations are welcomed and can be directed here.
Weekly updates are published in the USCG Local Notice to Mariners
which can be found here.
Mariners and the public are reminded that due to the
nature of the construction activities, project vessels may be
restricted in their ability to maneuver. It is requested that mariners
communicate with project vessels on Channel 16 VHF to coordinate any
necessary passing arrangement. Safety vessels will be on scene to
assist with the coordination of commercial and public marine traffic
and project vessels.
We remain committed to maintaining communications with
fishing communities and other mariners in the area via these periodic
updates, informational speaking engagements and dock visits. This
information is also posted on the
CVOW
website.
June Current and Planned
Operations
- Monopile installation activities will continue in the
west-northwest area of the CVOW site
- Rock placement may begin at the end of the month
- Munitions
and Explosives of Concern (MEC) relocation
- Light
marine debris
relocation in
support of MEC activities
- Nearshore construction approximately 400 yards off the
coast of the State Military Reservation (SMR)
- Multiple large project components are scheduled for
arrival at Portsmouth Marine Terminal
- Ongoing fisheries resource studies in and around the Lease
Area
|
|
Project Background Information
CVOW is a 2.6-gigawatt offshore wind energy project that will
consist of 176 wind turbines located 27 miles off the coast of
Virginia Beach, three offshore substations, undersea cables and new
onshore transmission infrastructure to deliver emissions-free wind
power to homes and businesses.
|
|
|
CVOW Marine Coordination Center
The CVOW project established a shoreside Marine
Coordination Center (MCC) to monitor and coordinate all offshore
activity related to project construction and operations. The MCC is
manned 24 hours a day, 7 days a week.
|
|
Offshore Installation
Activities |
|
Monopile Installation
M/V Orion completed the installation of the first monopile
foundation on May 22.
For ongoing installation, M/V Orion will load monopiles at
Portsmouth Marine Terminal and then transit to the site for
installation. The M/V Atlantic Oceantic and M/V Go Patriot will also
provide support.
|
|
|
Temporary Marine Lighting on Monopile Foundations
Once monopiles are installed in the seabed, temporary
quick flashing yellow marine navigation lights will be installed and
operated until the transition piece is permanently affixed to the
structure and the final lighting is installed, which could be as long
as six months.
Monopile foundations extend 15 – 20 feet above the sea,
and extreme caution should be exercised when operating in the
area.
For up-to-date status of foundation and lighting
installations, please reference the current USCG Local Notice to
Mariners.
|
|
|
Rock Placement Around Foundations
Near the end of June, scour protection installation activities may
begin around the monopile foundations.
A specialized rock placement vessel—either the M/V
Flint Stone or the M/V Yellow Stone—will lay rock (scour
protection) around the base of the monopiles, out to a diameter of
approximately 70-90 feet, based on specific site conditions.
Further details, such as the start of rock placement, will be
published in the USCG Local Notice to Mariners as plans are
finalized.
|
|
|
USCG Safety Zones In Effect
The U.S. Coast Guard has established 179 temporary
500-meter safety zones around the construction of 176 wind turbine
generators and three offshore substations in Federal waters on the
Outer Continental Shelf.
Each will be enforced individually for a period lasting
approximately 48 hours as construction progresses from one structure
to the next.
|
|
|
Buoy Installations
Scientific measurement buoys will be deployed in the
lease area for the duration of construction. The buoys will be
deployed from the M/V Go Freedom.
These devices will be gathering data such as
meteorological conditions, acoustic measurements and sound field
verifications. These buoys will be migrating throughout the lease area
and export corridor during construction.
|
|
Offshore Export Cable
Corridor |
|
Munitions and Explosives of Concern (MEC) Relocation
M/V HOS Mystique and HOS Bayou will continue MEC relocation
activities, as well as debris relocation, in and around the export
cable corridor offshore. Efforts in the northern section of the Lease
area are to follow.
The M/V Northstar Navigator will be conducting light
debris relocation work throughout the offshore export cable
corridor. The use of remote-operated vehicles (ROVs) and the
associated cabling necessitates an exclusion area, requested to be
~¼-mile (500m)
|
|
|
USCG Safety Zones
The U.S. Coast Guard has established a temporary safety
zone for navigable waters within a 1,000-yard radius of MEC Project
Vessels.
Operations are planned to relocate MEC in the Atlantic
Ocean, within 12 miles of the shores of the State Military Reservation
in Virginia Beach. Entry of vessels or persons into this zone is
prohibited unless specifically authorized by the Captain of the Port,
Sector Virginia or a designated representative
Operations will also be conducted in other areas outside
of the boundary.
|
|
|
Direct Pipe® Punchout Construction
Installations for Direct Pipe® conduit
installations are planned to continue through July with a scheduled
completion in August 2024. Installations of the TJBs will continue
throughout the remainder of 2024 and into early 2025.
The red area indicates the USCG Safety Zone in effect
during the nearshore construction efforts when construction vessels
are present. Mariners are requested to provide a 500-yard stand-off
distance from these activities.
|
|
Current Planned
Marine Vessel Spread for Nearshore Construction
|
Vessel
|
Lift
Type
|
Support
Activity
|
Homeport
|
Ram XII |
Lift
Boat |
Dive
Support |
Norfolk,
VA |
Go
Glory |
OSV |
Supplies
Transport |
Fourchon,
LA |
Josephine K.
Miller |
OSV |
Excavation |
Staten Island,
NY |
Angeline |
Tug |
HDPE
Tow |
Norfolk,
VA |
Robert
T |
Tug |
HDPE
Tow |
Norfolk,
VA |
Katan |
Tug |
HDPE
Tow |
Norfolk,
VA |
|
|
There are several scheduled arrivals of components to Portsmouth
Marine Terminal (PMT) in June, including eight monopiles via the M/V
Sun Shine.
M/V Orion will transit outbound from PMT to the lease area with up
to six monopiles at a time for installation activities.
|
|
Fisheries Resources
Characterization Studies |
|
Access to the lease area for recreational activities is
unrestricted unless construction activities are active, in which case
a 500-meter standoff distance is requested.
For questions about access, the F/V Atlantic Bounty is the on-site
project safety vessel and can provide direction. Mariners are reminded
not to touch or tie off to monopiles and to remain vigilant for other
vessels in the area.
|
|
|
The latest list of vessels supporting the project in MEC
relocation and disposition, transportation and installation, and
surveys can be found here.
|
|
|
Ron
Larsen
Fisheries Liaison Officer Sea Risk Solutions
(570) 242-5023
[email protected]
|
|
|
Michael
Lewis
CVOW Marine Affairs Manager Dominion Energy
(757) 236-8222
[email protected]
|
|
If you would
like more information on Coastal Virginia Offshore Wind (CVOW),
please visit our project website. |
|
|
|